The city was awarded a grant for a new hvac system for the MLK building. As a result there had to be an environmental study of the facility. They found a form of mold in the building. The first step was to remediate the mold. This required the building to be remediated from floor to ceiling including all duct work. At this time the staff was relocated to another city building and activities and sports had to take place at other location around the city. This took about a year to complete. The new HVAC installation project began March of 23 and was completed March of 24, 2024.